Pollution Prevention and Reduction
-
Collection System Improvements
61,921 FEET OF REHABBED SANITARY SEWER LINE20,002 FATS, OILS AND GREASE EDUCATIONAL MATERIALS DISTRIBUTED110,645 FEET OF SANITARY SEWER CLEANED-
Clean 10% of sanitary sewer mains annually
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
2018 Initiatives
2017 Initiatives
2016 Initiatives
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
NCDOT
Schedule
N/A
-
Perform fats, oils, and grease education distributions annually for the watershed
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2018 Initiatives
2017 Initiatives
2016 Initiatives
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
2018 Initiatives
NCDOT
Schedule
N/A
-
Inspect one pretreatment facility bi-annually in watershed to ensure proper disposal procedures
Burlington
Schedule
N/A
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
NCDOT
Schedule
N/A
-
Assess the effectiveness of the pretreatment program and provide recommended improvements to the Water Resources Department
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT
Schedule
N/A
-
Inspect high priority sanitary sewer lines in the watershed semi-annually
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
NCDOT
Schedule
N/A
-
Identify and prioritize I&I reduction projects for the watershed
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
2017 Initiatives
2016 Initiatives
NCDOT
Schedule
N/A
-
-
Erosion and Sediment Control
18 ACTIVE PERMITTED EROSION CONTROL SITES-
Issue violations for noncompliance under authority of delegated program
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
2018 Initiatives
Elon
Schedule
N/A
Graham
Schedule
N/A
2015 Initiatives
NCDOT
Schedule
N/A
-
Perform on-site inspections by Engineering Department for plan and permit compliance
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
2018 Initiatives
Elon
Schedule
N/A
Graham
Schedule
N/A
2019 Initiatives
2015 Initiatives
NCDOT
Schedule
N/A
-
Perform reviews of site plans and calculations by Engineering Department for proposed erosion and sediment controls
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
2018 Initiatives
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT
Schedule
N/A
-
Implement approved, delegated erosion and sediment control program administered by the Construction Program
Elon
Schedule
N/A
NCDOT - Complete
Schedule
Currently implemented, continue and adapt as necessary
-
Rely on State erosion and sediment control program administered by NCDENR
Burlington
Schedule
N/A
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
NCDOT
Schedule
N/A
-
Implement approved, delegated erosion and sediment control program administered by Engineering Department
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2016 Initiatives
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT
Schedule
N/A
-
-
Illicit Discharge Detection and Elimination
223 DUMPSTERS INSPECTED23,874 FEET OF STREAMS MONITORED-
Perform illicit discharge detection training for NCDOT and contractor staff in the watershed
Burlington
Schedule
N/A
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT - Complete
Schedule
Currently implemented, continue and adapt as necessary
-
Perform inspections of locations in the watershed where sanitary sewer cross-contamination may occur.
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
NCDOT
Schedule
N/A
-
Perform analytical monitoring of 5 sites in the watershed
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT
Schedule
N/A
-
Perform inspections of dumpsters in the watershed for proper use and structural adequacy once per permit cycle.
Burlington
Schedule
N/A
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implementing
NCDOT
Schedule
N/A
-
Perform annual inspections of 50% of the identified dumpsters for proper function
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2018 Initiatives
2015 Initiatives
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT
Schedule
N/A
-
Utilize the Burlington customer response program for fielding complaints about illegal dumping
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
2018 Initiatives
2017 Initiatives
2016 Initiatives
Elon
Schedule
N/A
Graham
Schedule
N/A
2019 Initiatives
2018 Initiatives
2017 Initiatives
2016 Initiatives
NCDOT
Schedule
N/A
-
Illegal dumping hotline
Burlington
Schedule
N/A
2019 Initiatives
2018 Initiatives
2017 Initiatives
2016 Initiatives
Elon
Schedule
N/A
Graham - Complete
Schedule
Continue to use the City’s primary number and direct calls to appropriate contacts
2019 Initiatives
2018 Initiatives
2017 Initiatives
2016 Initiatives
NCDOT
Schedule
N/A
-
Perform illicit discharge detection and elimination program under authority of ordinance
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2018 Initiatives
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
2018 Initiatives
2017 Initiatives
2015 Initiatives
NCDOT - Complete
Schedule
Currently implemented, continue and adapt as necessary
-
Perform annual representative outfall monitoring within the watershed for designated outfalls
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
Elon
Schedule
N/A
Graham
Schedule
Implement new program in FY 2020
NCDOT
Schedule
N/A
-
Perform dry weather flow stream walks for the intermittent and perennial streams in the watershed within each permit cycle
Burlington - Complete
Schedule
Currently implemented, continue as programmed
2019 Initiatives
2018 Initiatives
2015 Initiatives
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue as programmed
2019 Initiatives
2018 Initiatives
NCDOT
Schedule
N/A
-
-
Pollution Prevention and Good Housekeeping
29 CITY FACILITIES INSPECTED-
Train NCDOT staff and contractors on fertilizer management and nutrient application decisions
Burlington
Schedule
N/A
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT - Complete
Schedule
Currently implemented, continue and adapt as necessary
-
Stormwater pollution prevention and spill prevention and response training to NCDOT staff
Burlington
Schedule
N/A
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT - Complete
Schedule
Currently implemented, continue and adapt as necessary
-
Provision and update of Industrial and Roadway Maintenance Activities (IRMA) BMP Guidance Manual for activities performed within the ROW
Burlington
Schedule
N/A
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT - Complete
Schedule
Currently implemented, continue and adapt as necessary
-
Development of SWPPP for remaining facilities
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT
Schedule
N/A
-
Provide seasonal leaf and weekly yard waste collection to properties in the watershed
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2018 Initiatives
2017 Initiatives
2016 Initiatives
Elon
Schedule
N/A
NCDOT
Schedule
N/A
-
Inspect and clean catch basins as necessary to insure proper maintenance of the stormwater system
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
NCDOT
Schedule
N/A
-
Annual sweeping of curb and gutter streets in watershed
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2018 Initiatives
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
NCDOT
Schedule
N/A
-
Annual reviews of City-owned NPDES stormwater permitted facilities by Stormwater Consultant or Division
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
NCDOT
Schedule
N/A
-
New employee training on good housekeeping and IDDE
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
NCDOT
Schedule
N/A
-
Annual refresher training on good housekeeping and IDDE for targeted City employees
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
Elon
Schedule
N/A
Graham
Schedule
Currently implemented, continue and adapt as necessary
NCDOT
Schedule
N/A
-
Annual inspection of city owned facilities by Stormwater Division (or consultant) for compliance with Stormwater Pollution Prevention Plan (SWPPP)
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2015 Initiatives
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
NCDOT
Schedule
N/A
-
-
Post Construction Runoff Control Program
120 STORMWATER BMPs INSPECTED26 COMMUNITY STORMWATER BMPs INSTALLED-
Require developments that are greater than 10% of the upstream drainage area to match predevelopment runoff rates
Burlington
Schedule
N/A
Elon
Schedule
N/A
Graham - Complete
Schedule
Continued implementations of the City’s Storm Drainage Design Manual and reduce the upstream drainage limits within the watershed to 10% from the current 25%.
NCDOT
Schedule
N/A
-
Incorporate provisions for LID as part of Unified Development Ordinance revision
Burlington
Schedule
Implement new program in FY 2020
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT
Schedule
N/A
-
Require conformance to stormwater standards for new development and redevelopment projects
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
NCDOT
Schedule
N/A
-
Maintain the use of the Best Management Practices Toolbox for post-construction runoff control on NCDOT projects
Burlington
Schedule
N/A
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT - Complete
Schedule
Currently implemented, continue and adapt as necessary
-
Implement NCDOT’s Post-Construction Stormwater Program (PCSP) controls for roadway and non-roadway projects
Burlington
Schedule
N/A
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT - Complete
Schedule
Currently implemented, continue and adapt as necessary
-
Adopt Jordan Lake Rules by ordinance for new and development standards for the control of nutrients in post-construction runoff
Burlington
Schedule
Implement new program in accord with legislative implementation schedule
Elon
Schedule
N/A
Graham
Schedule
Implement new program in accord with legislative implementation
NCDOT
Schedule
N/A
-
Perform inspection of BMPs in the watershed utilizing NCDOT Stormwater Control Management System (SCMS) database
Burlington
Schedule
N/A
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT - Complete
Schedule
Currently implemented, continue and adapt as necessary
-
Within each permit cycle perform inspections of permitted structural BMPs in the watershed
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2015 Initiatives
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
NCDOT
Schedule
N/A
-
Receive and evaluate annual inspection reports submitted by owners for permitted structural BMPs in the watershed
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2015 Initiatives
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
NCDOT
Schedule
N/A
-
-
Stormwater Retrofits
2 RETROFIT PROJECTS COMPLETED8 POTENTIAL RETROFIT SITES IDENTIFIED-
Design and construct evaluated stormwater retrofits for watershed
Burlington
Schedule
N/A
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT
Schedule
Implement new program in FY 2018
-
Amend 50/50 Cost Share program to incorporate LID projects
Burlington
Schedule
Implement new program in FY 2017
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT
Schedule
N/A
-
Identify additional stormwater retrofits through watershed planning process
Burlington
Schedule
Implement new program in FY 2020
Elon
Schedule
N/A
Graham
Schedule
Implement new program in FY 2020
NCDOT
Schedule
N/A
-
Prioritize stormwater retrofits within the watershed
Burlington
Schedule
Implement new program in FY 2018
Elon
Schedule
N/A
Graham
Schedule
Implement new program in FY 2018
NCDOT
Schedule
N/A
-
Compile and maintain active list of stormwater retrofit opportunities for possible implementation
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented
NCDOT
Schedule
Implement new program in FY 2016
-
-
-
Public Involvement
-
Public Involvement & Outreach
124 HOURS OF DIRECT PUBLIC EDUCATION & OUTREACH12 STREAM CLEAN UPS71 PUBLIC EDUCATION EVENTS1 RAIN GARDENS INSTALLED WITHIN OUR COMMUNITY-
Promote stakeholder group meetings for proposed construction projects in watershed
Burlington
Schedule
N/A
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT - Complete
Schedule
Currently implemented, continue and adapt as necessary
-
Adopt-A-Highway program for NCDOT roads in the watershed
Elon
Schedule
N/A
NCDOT - Complete
Schedule
Currently implemented, continue and adapt as necessary
-
Promote Category 4b Demonstration Plan and activities through NCDOT social medias (Twitter/Facebook/RSS/ Flickr) and NCDOT Now (YouTube)
Burlington
Schedule
N/A
2019 Initiatives
2018 Initiatives
2017 Initiatives
Elon
Schedule
N/A
Graham
Schedule
N/A
2019 Initiatives
2018 Initiatives
2017 Initiatives
NCDOT
Schedule
Implement in FY 2016 and adapt as necessary
-
Post this watershed plan and other appropriate content on NCDOT’s Highway Stormwater Program website
Burlington
Schedule
N/A
2019 Initiatives
Elon
Schedule
N/A
Graham
Schedule
N/A
2019 Initiatives
NCDOT
Schedule
Implement in FY 2016 and adapt as necessary
2017 Initiatives
-
Develop specific watershed content for Stormwater Division’s website
Burlington - Complete
Schedule
Currently implemented
2021 Initiatives
2017 Initiatives
2016 Initiatives
Elon
Schedule
N/A
Graham
Schedule
N/A
2017 Initiatives
2016 Initiatives
NCDOT
Schedule
N/A
2017 Initiatives
2016 Initiatives
-
Develop Green Infrastructure Grant Program for targeted areas in the watershed
Burlington
Schedule
Implement new program in Year 3
Elon
Schedule
N/A
NCDOT
Schedule
N/A
-
Promote water quality programs for Summer Camp performed by the Recreation Department
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2018 Initiatives
2017 Initiatives
Elon
Schedule
N/A
NCDOT
Schedule
N/A
-
Promote proper disposal of E-Waste and collection events in watershed
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
2018 Initiatives
2016 Initiatives
Elon
Schedule
N/A
NCDOT
Schedule
N/A
-
Organize and publicize stream clean up in watershed
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
2018 Initiatives
2017 Initiatives
2016 Initiatives
2015 Initiatives
Elon
Schedule
N/A
Graham
Schedule
N/A
2019 Initiatives
2018 Initiatives
2017 Initiatives
2016 Initiatives
2015 Initiatives
NCDOT
Schedule
N/A
2017 Initiatives
2016 Initiatives
-
Document Burlington customer response program, stormwater, and stream-related solicitations in watershed
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
2018 Initiatives
2017 Initiatives
2016 Initiatives
Elon
Schedule
N/A
Graham
Schedule
N/A
2019 Initiatives
2018 Initiatives
2017 Initiatives
2016 Initiatives
NCDOT
Schedule
N/A
-
Leverage the quarterly CityWorks newsletter distributed with utility bills to inform the public of the Category 4b Demonstration Plan and their potential involvement in nonpoint source pollution reduction
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2018 Initiatives
2017 Initiatives
2016 Initiatives
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT
Schedule
N/A
-
Partner with Alamance County Cooperative Extension on rain garden education and construction in watershed
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
2018 Initiatives
2016 Initiatives
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
NCDOT
Schedule
N/A
-
Prioritize projects identified through the 50/50 Cost Share Program in the watershed
Burlington - Complete
Schedule
Adapt current program in FY 2017
2018 Initiatives
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
NCDOT
Schedule
N/A
-
Perform stormwater-related presentations for civic groups
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
2018 Initiatives
2017 Initiatives
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
2018 Initiatives
2017 Initiatives
-
In cooperation with Burlington and Graham distribute pollution prevention educational materials through NCDOT’s Office of Beautification during local fairs/Earth Day celebrations/and other appropriate community events
Burlington
Schedule
N/A
2018 Initiatives
2017 Initiatives
Elon
Schedule
N/A
Graham
Schedule
N/A
2018 Initiatives
2017 Initiatives
NCDOT
Schedule
Implement in FY 2016 and adapt as necessary
2017 Initiatives
-
Attend festivals/parades/events with stormwater-related staff for public engagement
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2018 Initiatives
- 11th Annual Yee-Haw! River Paddle
- Nature Hike at Shallow Ford Natural Area – Postponed – New Date- April 21
- Creek Week Water Trivia Night
- Creek Week Water Trivia Night!
- Creek Week Trivia Night!
- ‘Creek Life’ Preschool Storytime: May Memorial Public Library
- Nature Hike at Glencoe Paddle Access
- Family Stream Training: Haw River Assembly
- Painted Grape: Water-Themed Painting Classes!
- City Park BMP Tour HydroVault Demonstration
2017 Initiatives
2016 Initiatives
2015 Initiatives
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
2019 Initiatives
2018 Initiatives
- Family Fishing Fun!
- ‘Creek Life’ Toddler Storytime: Graham Public Library
- Creek Week Water Trivia Night!
- City of Graham Wastewater Treatment Plant Tour
- Creek Week Trivia Night!
- ‘Creek Life’ Preschool Storytime: Graham Public Library
- Alamance Creek Week 2018
- Creek Week Campus Clean-ups: South Graham Elementary School
2016 Initiatives
NCDOT
Schedule
N/A
-
Conduct Annual Stormwater Meeting for public feedback and solicitation
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
2016 Initiatives
NCDOT
Schedule
N/A
-
Partner with Piedmont Triad Water Quality Partnership as a regional, broad-based stormwater education provider
Burlington - Complete
Schedule
Currently implemented, continue as programmed
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented
NCDOT
Schedule
N/A
-
Partner with the Stormwater Management and Recovery of the Triad (SMART) program as a regional, broad-based stormwater education provider
Burlington - Complete
Schedule
Currently implemented, continue as programmed
2018 Initiatives
2017 Initiatives
2016 Initiatives
2013 Initiatives
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue as programmed
2019 Initiatives
2018 Initiatives
2017 Initiatives
NCDOT
Schedule
N/A
-
-
Research
2 RESEARCH PROJECTS FUNDED WITHIN THE WATERSHED-
Evaluate new opportunities to initiate a stormwater research project within watershed
Burlington
Schedule
N/A
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT
Schedule
Evaluate in FY 2018
-
Leverage findings from NCDOT’s Research and Analysis Program for improvements to design or maintenance of pollution controls in the watershed
Burlington
Schedule
N/A
2017 Initiatives
Elon
Schedule
N/A
Graham
Schedule
N/A
2017 Initiatives
NCDOT - Complete
Schedule
Currently implemented, continue and adapt as necessary
-
Develop partnership with Elon University for collaborative research services in watershed
Burlington
Schedule
Implement new program in FY 2017
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT
Schedule
N/A
-
Continue participation in the Stormwater Group through the North Carolina Water Resources Research Institute
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT
Schedule
N/A
-
-
-
Stream Enhancement
-
Stream Buffers
100% PERCENT OF STREAMS PROTECTED BY RIPARIAN BUFFER ORDINANCE-
Require conformance to stream buffer standards for new and existing developments
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
2016 Initiatives
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
2016 Initiatives
-
Implement GREEN Program for New Development projects in watershed
Burlington
Schedule
N/A
2017 Initiatives
Elon
Schedule
N/A
Graham
Schedule
N/A
2017 Initiatives
NCDOT - Complete
Schedule
Currently implemented, continue and adapt as necessary
-
Enforce violations of stream buffer standards under authority of ordinance
Burlington - Complete
Schedule
Currently implemented, continue and adapt as necessary
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented, continue and adapt as necessary
NCDOT
Schedule
N/A
-
-
Stream Restoration and Enhancement
5.84 MILES OF STREAM CLEANED16,425 POUNDS OF TRASH COLLECTED FROM STREAM CLEAN-UPS3,785 FEET OF STREAMS RESTORED3,323 FEET OF STREAM IDENTIFIED FOR POSSIBLE RESTORATION OPPORTUNITIES-
Amend 50/50 Cost Share program to incorporate the evaluation of streambank stabilization
Burlington
Schedule
Implement new program in FY 2019
Elon
Schedule
N/A
Graham
Schedule
N/A
NCDOT
Schedule
N/A
-
Identify additional stream restoration and streambank stabilization opportunities through watershed planning
Burlington
Schedule
Implement new program FY 2020
Elon
Schedule
N/A
Graham
Schedule
Implement new program FY 2012
NCDOT
Schedule
N/A
-
Coordinate with funding agencies to identify and evaluate potential projects from list
Burlington
Schedule
Implement new program in FY 2018
Elon
Schedule
N/A
Graham - Complete
Schedule
Currently implemented
NCDOT
Schedule
N/A
-
Compile and maintain active list of stream restoration and streambank stabilization opportunities for possible implementation
Burlington
Schedule
Implement new program in FY 2017
Elon
Schedule
N/A
Graham
Schedule
Implement new program in FY 2016
NCDOT
Schedule
N/A
-
-
-
Stream Health
-
Aquatic Life
-
Water Quality Monitoring
5 WATER QUALITY SAMPLING SITES26 WATER QUALITY SAMPLES TAKEN AT EACH SITE
-